Module 4 of 5
Assessing and Managing Asset Management Risks
A small vocabulary, examined with precision. Several of the terms are pairs that differ by one idea, and the questions are built around exactly that difference.
At a glance
- Module minimum
- 50% - a weak module fails you on its own
- Overall pass mark
- 65% across all five modules
- On this page
- Free summary and 6 practice questions
Summary
What this module covers
Module 4 carries 10 questions. Its vocabulary is compact but tightly defined, and most of the marks go to getting the pairs and the sequence right.
Appetite and tolerance
Risk appetite is how much risk an organisation is willing to take in pursuit of its objectives. Risk tolerance is how much it is able to bear. The two can differ widely. An organisation with a large appetite and a small tolerance is heading for trouble. Appetite also isn't a single number, because organisations take different views of different kinds of risk. Without a stated appetite there is no consistent basis for deciding what to accept, and decisions end up depending on who happens to be making them.
The process, in order
Identify the risk, analyse it, evaluate it, treat it. Then monitor and review, because the picture keeps changing.
Analysis works out the level of risk by combining likelihood and consequence. Evaluation compares that level against criteria and appetite to decide whether it is acceptable and how urgently it needs attention. Getting these two the wrong way round is the most common ordering error.
Identification techniques are worth knowing by purpose. HAZOP works systematically through a process, applying guide words to find hazards and operability problems. FMEA works through failure modes and their effects. FMECA adds criticality, which turns the list into a ranking.
Treatment options
Four responses, often called the four Ts:
- Tolerate — accept the risk, with a recorded rationale
- Treat — reduce the likelihood or the consequence
- Transfer — share the financial consequence, typically through insurance or contract
- Terminate — stop the activity that creates the risk
Transfer moves the cost, not the accountability. The event still happens and the service is still disrupted. The same principle applies when work is contracted out: the activity moves to the contractor, but accountability stays with the organisation.
Criticality, residual risk and contingency
Criticality ranks assets by the consequence of their failure, so that effort can be prioritised consistently. It is not the same as condition. A sound valve that is the only feed to a hospital usually deserves more attention than a worn one on a lightly used branch. Residual risk is what remains after controls are in place, and it is what should be compared with appetite. Inherent risk is the exposure before controls.
A contingency is a possible future event that cannot be predicted with certainty, for which a response is prepared in advance. Plans need defined triggers, such as a critical asset failing or a quality measure crossing a threshold, so that invoking them is a decision rather than an argument.
Where marks are lost
- Swapping appetite and tolerance
- Putting evaluation before analysis
- Believing insurance or a contract transfers accountability
- Ranking assets by condition when the question is about criticality
- Treating a risk as eliminated and in no further need of review
Practice
Practice questions
Six questions in the exam format: five options, one correct answer. Each one explains why the right answer is right and why the other four are wrong. Nothing is recorded and nothing is stored on your device.
The pack
The complete revision pack
£19
- 22 pages of my handwritten notes, as a PDF
- 150 original practice questions, scored per module
- A timed mock of 60 questions in two hours, working offline
One payment covers both files. The download link arrives by email straight after.